Our garage
THIS YEAR'S GARAGE WILL BE 16' BY 24'. THE STUDENTS WILL FRAME, SIDE, SHINGLE, HANG THE DOORS, INSTALL THE WINDOWS AND INSTALL THE GARAGE DOOR OPENER.
GETTING STARTED
. PLANS
.
FRONT VIEW
.
BACK VIEW
.
FORMING FOR CONCRETE
.
CONCRETE IN
.
CONCRETE IN...ALONG WITH TUBING FOR ELECTRICAL
.
THE CONTRACTORS
.
BOLTING THE SILL BOARD DOWN
.
FIRST WALL GOES UP
.
SHOWING CHALK LINE FOR FRAMED WALL
.
LIFTING END WALL IN PLACE
.
END WALL UP
.
NAILING A WALL TOGETHER (CORNER UNIT BEING WORKED ON)
.
NAILING THE DOUBLE TOP PLATE IN PLACE
.
WALLS ARE UP!
.
MARKING FOR TRUSS PLACEMENT
.
INSTALLING THE HOUSE WRAP
.
STARTING TO SET THE TRUSSES
.
ALMOST DONE WITH THE TRUSSES
.
CLOSING IN THE GABLE END
.
BUILDING THE GABLE OVERHANG
.
INSTALLING THE GABLE OVERHANG
.
STRAIGHTENING THE FASCIA
.
READY TO SHEET THE ROOF
.
SHEETING THE ROOF
.
INSTALLING THE WINDOW
.
ROOF BLACKED IN AND READY FOR SHINGLES
.
GUTTER APRON & DRIP CAP ON, STARTING TO SHINGLE
.
SHINGLING THE ROOF
.
SHINGLING THE ROOF
.
ROOF SHINGLED, GUTTER APRON AND DRIP EDGE ON
.
CALKING AND SETTING THE WALK IN DOOR
.
DOOR SET AND READY TO BE NAILED INTO PLACE
.
CUTTING SOFFIT MATERIAL TO LENGTH
.
PUTTING "F" CHANNEL UP FOR THE SOFFIT
.
PUTTING SOFFIT MATERIAL UP
.
PUTTING SOFFIT MATERIAL UP
.
PUTTING FASCIA MATERIAL UP
.
NORTH SIDE TRIMMED OUT :-)
.
FINISHING UP FASCIA AND SOFFIT
.
STARTING TO INSTALL THE GARAGE DOOR
.
INSTALLING THE OVERHEAD DOOR TRACK
.
INSTALLING THE OVERHEAD DOOR SPRING
.
INSTALLING VINYL SIDING
.
INSTALLING VINYL SIDING
.
Crete Public Schools
and
Educational Service Unit #6, Milford, Nebraska
|